YC1 Gantry Protective Coating Repairs
Gladstone, Queensland, Australia
- Client:
- Wiggins Island Coal Export Terminal
- Duration:
- 38 Months
- Completed:
- May 2024
Complete coating patch repairs on gantry stacker girders and associated structural elements from top of rail to 1m below rail level. The work scope comprises the following:
- Establish access platforms to the underside of the gantry structure
- Undertake coating inspections to determine location of patch repairs
- Complete corrosion repairs (pad welding)
- Complete localised abrasive blasting works to remove coating defects
- Apply new coating system to localised patch repairs
- Relocate access platforms