HPX3 –Shutdown 6 and Temporary Works Removal

Location: Hay Point Coal Terminal
Owner: BM Alliance Coal Operations
Client: Bechtel Australia Pty Ltd
Project Value: $14million
Duration: 7 months
Peak Labour Force: 75 personnel

Bechtel engaged the Walz Group in June 2015 to provide marine equipment and personnel for their Hay Point Expansion Project Phase 3 (HPX3) offshore shutdown 6 (SD6) and temporary works removal.

Walz Group provided the following:

Throughout the project, Walz Group continually adapted to changing weather conditions and schedule changes, and successfully met all milestone dates via a flexible approach to resourcing and positive client engagement.